Project Description:
LAWRENCE- LAWRENCE MANCHESTER RAIL CORRIDOR (LMRC) RAIL TRAIL
The proposed improvements include redeveloping the inactive Lawrence Manchester Rail Corridor into a shared-use path / alternate transportation corridor (ATC) for pedestrian and bicycle accommodations. The 1.40 mile project begins at Merrimack Street in Lawrence and extends to the Methuen/Lawrence City Line. The ATC will connect Merrimack Street to the south and Manchester Street Park, the Spicket River Greenway, and the future Methuen Rail Trail to the north. The project also includes improving 3 intersections for at-grade crossings, and developing additional access points to the Rail Trail from existing developments and parks. There are four bridges along the Right-of-Way that will be improved as part of the project including deck replacements at bridges over the South Canal and the Merrimack River, complete replacement of the Lowell Street Bridge that spans the Right of Way, and a superstructure replacement at the Manchester Street Bridge Crossing.
Location:
  • City of Lawrence
  • Design Responsibility: Municipality
    Construction Begins: Winter 2024/2025
    Project Manager: Lawrence Cash
    Estimated Total Contract Cost: $29,045,564.00
    Estimated Total Federal Participating Construction Cost: $30,504,506.50
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Merrimack Valley Metropolitan Planning Organization.
    District: District 4
    Current Status: This project has been advertised for construction bids. (as of 09/07/2024 )

    Contracts (3) Progress
    # 102485 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide road and bridge projects, for the purpose of mainta Final
    # 115795 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77878 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Merrimack Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: LAWRENCE
    Category: Advertised Projects Constr.
    Budget Section: 2C
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) $21,416,304 CMAQ (inflated 4% from 2023 cost); c) AC Year 1-2 FFY 2024-2025: d) TEC = 11.25 out of 18.
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $6,161,280.00
    State Cost: $1,540,320.00
    Total Cost: $7,701,600.00

    Planned Federal FY: 2026
    Responsible MPO: Merrimack Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: LAWRENCE
    Category: Advertised Projects Constr.
    Budget Section: 2C
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) $21,416,304 CMAQ (inflated 4% from 2023 cost); c) AC Year 1-2 FFY 2024-2025: d) TEC = 11.25 out of 18.
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $6,400,000.00
    State Cost: $1,600,000.00
    Total Cost: $8,000,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/15/2017
    Project Need Form PNF Approved 11/15/2017
    Project Initiation Form PIF Entered 11/15/2017
    Project Initiation Form PIF Approved 11/15/2017
    Project Initiation Form PRC Submitted 11/15/2017
    Project Review Committee PRC Approved 12/14/2017
    Project Status Advertised 09/07/2024
    Project Management
    100% Design 100% Package Received 12/04/2023
    100% Design 100% Package Comments to DE 01/24/2024
    25% Design 25% Package Received 02/19/2021
    25% Design 25% Package Comments to DE 06/17/2021
    25% Design Design Public Hearing 07/21/2022
    75% Design 75% Package Received 10/31/2022
    75% Design 75% Package Comments to DE 03/14/2023
    Final Design PS&E Received 08/12/2024
    Final Design PS&E Received - Resub 1 08/26/2024
    Consultant Contract Process NTP Issued 05/24/2018