Project Description:
PEABODY- REHABILITATION OF CENTRAL STREET
The project will rehabilitate Central Street from Walnut Street to Andover Street and Pulaski Street from Andover Street to Gardner Street including full depth reclamation/reconstruction of the pavement structure, intersection reconstruction, reconstruction of cement concrete sidewalks and crossings, addition of dedicated bicycle accommodations, signage and pavement marking improvements, streetscape enhancements, and drainage system improvements corridor-wide. The intersections of Central Street at Tremont Street, Central Street at Warren Street, Central Street at Andover Street, and Pulaski Street at Gardner Street will be reconstructed and all traffic signal equipment will be upgraded to optimize lane designation for proper flow through the corridor.
Location:
  • City of Peabody
  • Construction Begins: Winter 2023/2024
    Resident Engineer: James Vayanos
    Construction Bid Price: $18,716,724.16
    District: District 4

    Contracts (2) Progress
    # 115797 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 123965 -- Construction Contract
    Rehabilitation of Central Street 6% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/29/2023
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/16/2017
    Project Need Form PNF Approved 11/14/2017
    Project Initiation Form PIF Entered 11/16/2017
    Project Initiation Form PIF Approved 11/16/2017
    Project Initiation Form PRC Submitted 11/16/2017
    Project Review Committee PRC Approved 12/14/2017
    Project Status Advertised 09/02/2023
    Project Management
    100% Design 100% Package Received 03/29/2023
    100% Design 100% Package Comments to DE 05/02/2023
    25% Design 25% Package Received 05/11/2020
    25% Design 25% Package Comments to DE 08/11/2020
    25% Design Design Public Hearing 06/23/2021
    75% Design 75% Package Received 07/01/2022
    75% Design 75% Package Comments to DE 08/15/2022
    Final Design PS&E Received 08/14/2023
    Final Design PS&E Received - Resub 1 08/25/2023
    Final Design PS&E Received - Resub 2 08/31/2023