Project Description:
PEABODY- REHABILITATION OF CENTRAL STREET
Location:
  • City of Peabody
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2022/2023
    Project Manager: Greg Frazier
    Estimated Total Contract Cost: $16,978,860.55
    Estimated Total Federal Participating Construction Cost: $15,219,860.20
    Funding Provision: This project is planned to be funded through the 2023 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: 25% Package Comments to DE (as of 08/11/2020 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2023
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: PEABODY
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction; CMAQ+HSIP+STBG Total Cost = $10,432,800; MPO Evaluation Score = 61
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $1,350,000.00
    State Cost: $150,000.00
    Total Cost: $1,500,000.00

    Planned Federal FY: 2023
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: PEABODY
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction; CMAQ+HSIP+STBG Total Cost = $10,432,800; MPO Evaluation Score = 61
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $2,400,000.00
    State Cost: $600,000.00
    Total Cost: $3,000,000.00

    Planned Federal FY: 2023
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: PEABODY
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • STBG revised from $5,932,800 to $11,328,654 via STIP Action 6.
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $9,062,923.20
    State Cost: $2,265,730.80
    Total Cost: $11,328,654.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/16/2017
    Project Need Form PNF Approved 11/14/2017
    Project Initiation Form PIF Entered 11/16/2017
    Project Initiation Form PIF Approved 11/16/2017
    Project Initiation Form PRC Submitted 11/16/2017
    Project Review Committee PRC Approved 12/14/2017
    Project Management
    25% Design 25% Package Received 05/11/2020
    25% Design 25% Package Comments to DE 08/11/2020