Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CONCORD- LINCOLN- ROUTE 2 CROSBY CORNER WETLAND MITIGATION
Project is in response to deficiencies found in BMPs constructed through Crosby Corner Project. Proposed BMP will intercept existing storm water from state drainage system.
Location:
  • Town of Concord
  • Town of Lincoln
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Gautam Sen
    Estimated Total Contract Cost: $187,000.00
    Estimated Total Federal Participating Construction Cost: $212,500.00
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (1) Progress
    # 77848 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/17/2017
    Project Need Form PNF Approved 11/17/2017
    Project Initiation Form PIF Entered 11/17/2017
    Project Initiation Form PIF Approved 11/17/2017
    Project Initiation Form PRC Submitted 02/21/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Management