Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WELLFLEET- CAPE COD RAIL TRAIL EXTENSION
The project will expand the fully accessible, developed extent of the Cape Cod Rail Trail northward for approximately 2 miles toward Wellfleet center with a connecting path to DCR’s new Paine Campground. This will provide a multi-modal, off-road, bicycle and pedestrian connection from the existing 24-mile Cape Cod Rail Trail to Wellfleet. The proposed cross-section will mimic the existing CCRT. This project include one at-grade road crossing at Old Kings Highway. The project will also include a new parking and trailhead area at Route 6 in Wellfleet.
Location:
  • Town of Wellfleet
  • Design Responsibility: Other
    Right of Way Responsibility: Other
    Project Manager: Pamela Haznar
    Estimated Total Contract Cost: $2,750,000.00
    Estimated Total Federal Participating Construction Cost: $3,000,000.00
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/17/2017
    Project Need Form PNF Approved 11/16/2017
    Project Initiation Form PIF Entered 11/17/2017
    Project Initiation Form PIF Approved 11/17/2017
    Project Initiation Form PRC Submitted 11/29/2017
    Project Review Committee PRC Approved 12/14/2017
    Project Management