Project Description:
BOSTON- NEPONSET RIVER GREENWAY CONSTRUCTION, INCLUDING NEW BRIDGE B-16-309 (C6Y) OVER DORCHESTER BAY
The proposed project includes construction of a 10-foot wide shared-use path with 2-foot shoulders, from Tenean Beach to Morrissey Boulevard, a total distance of approximately 3,600 feet. A 670-foot long boardwalk, including scenic overlooks, will be constructed to convey the path over salt marsh and tidal habitat of the Dorchester Bay. Drainage system improvements, enhanced landscaping, wood guardrail, signs and pavement markings are also proposed. This project is a critical segment in DCR’s long term, multi-phase, plan for the 10.5-mile Neponset River Greenway linking the Blue Hills Reservation in Milton to Mattapan Square and continuing to Castle Island and the Boston Harborwalk.
Location:
  • City of Boston
  • Construction Begins: Winter 2022/2023
    Resident Engineer: Patrick Finn
    Construction Bid Price: $8,845,076.00
    District: District 6

    Contracts (1) Progress
    # 120181 -- Construction Contract
    Construction of a Shared Use Path (Neponset River Greenway) Including Boardwalk Construction Br. No. B-16-309 (Prefabricated Aluminum Truss) over Dorchester Bay 50% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 01/18/2023
    Contract Information
    Project Designer: Other
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/17/2017
    Project Need Form PNF Approved 11/16/2017
    Project Initiation Form PIF Entered 11/17/2017
    Project Initiation Form PIF Approved 11/17/2017
    Project Initiation Form PRC Submitted 11/17/2017
    Project Review Committee PRC Approved 12/14/2017
    Project Status Advertised 09/10/2022
    Project Management
    100% Design 100% Package Received 11/24/2021
    100% Design 100% Package Comments to DE 01/05/2022
    25% Design 25% Package Received 05/29/2020
    25% Design 25% Package Received 05/29/2020
    25% Design 25% Package Comments to DE 10/05/2020
    25% Design Design Public Hearing 05/26/2021
    75% Design 75% Package Received 05/29/2020
    75% Design 75% Package Comments to DE 10/05/2020
    Final Design PS&E Received 06/14/2022
    Final Design PS&E Received - Resub 1 08/15/2022