Project Description:
BOSTON- NEPONSET RIVER GREENWAY CONSTRUCTION, INCLUDING NEW BRIDGE B-16-309 (C6Y) OVER DORCHESTER BAY
Location:
  • City of Boston
  • Design Responsibility: Other
    Construction Begins: Autumn 2022
    Project Manager: Courtney Worhunsky
    Estimated Total Contract Cost: $8,506,510.06
    Estimated Total Federal Participating Construction Cost: $8,809,271.69
    Funding Provision: This project is planned to be funded through the 2022 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: Design Public Hearing (as of 05/26/2021 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2022
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BOSTON
    Category: Advertised Projects Constr.
    Budget Section: 2C
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $4,457,303.20
    State Cost: $1,114,325.80
    Total Cost: $5,571,629.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/17/2017
    Project Need Form PNF Approved 11/16/2017
    Project Initiation Form PIF Entered 11/17/2017
    Project Initiation Form PIF Approved 11/17/2017
    Project Initiation Form PRC Submitted 11/17/2017
    Project Review Committee PRC Approved 12/14/2017
    Project Management
    25% Design 25% Package Received 05/29/2020
    25% Design 25% Package Received 05/29/2020
    25% Design 25% Package Comments to DE 10/05/2020
    25% Design Design Public Hearing 05/26/2021
    75% Design 75% Package Received 05/29/2020
    75% Design 75% Package Comments to DE 10/05/2020