MANSFIELD- RECONSTRUCTION ON CHAUNCY STREET (ROUTE 106)
Location:
  • Town of Mansfield
  • Design Responsibility: Municipality
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2024
    Project Manager: Gautam Sen
    Estimated Total Contract Cost: $2,428,377.50
    Estimated Total Federal Participating Construction Cost: $2,736,690.00
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: 25% Package Received (as of 03/19/2021 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: MANSFIELD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) Total Cost = $5,600,000 STBG; d) EC Score 59 of 100; i) Status Pre 25%
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $4,480,000.00
    State Cost: $1,120,000.00
    Total Cost: $5,600,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/20/2017
    Project Need Form PNF Approved 11/16/2017
    Project Initiation Form PIF Entered 11/20/2017
    Project Initiation Form PIF Approved 11/20/2017
    Project Initiation Form PRC Submitted 11/29/2017
    Project Review Committee PRC Approved 12/14/2017
    Project Management
    25% Design 25% Package Received 03/19/2021