Project Description:
CHELSEA- BRIDGE SUPERSTRUCTURE REPLACMENT C-09-013, WASHINGTON AVENUE, CARTER STREET & COUNTY ROAD/ROUTE 1
Location:
  • City of Chelsea
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2025
    Project Manager: Anni H Autio
    Estimated Total Contract Cost: $18,711,799.95
    Estimated Total Federal Participating Construction Cost: $19,652,051.80
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: 25% Package Received (as of 02/20/2023 )

    Contracts (2) Progress
    # 115745 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77846 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: CHELSEA
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Next Generation Bridge GANs
    Federal Cost: $8,467,200.00
    State Cost: $2,116,800.00
    Total Cost: $10,584,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/21/2017
    Project Need Form PNF Approved 11/21/2017
    Project Initiation Form PIF Entered 11/21/2017
    Project Initiation Form PIF Entered 05/01/2020
    Project Initiation Form PIF Approved 11/21/2017
    Project Initiation Form PRC Submitted 11/21/2017
    Project Initiation Form PRC Submitted 04/30/2020
    Project Review Committee PRC Tabled 08/15/2019
    Project Review Committee PRC Approved 04/30/2020
    Project Management
    25% Design 25% Package Received 02/20/2023