Project Description:
WORCESTER- INTERSECTION IMPROVEMENTS ON CHANDLER STREET AND MAY STREET
The limits of this project are bound by Hamill Street and it's intersection with Chandler and May Street to a point approximately 1200 feet west of the northerly intersection of Chandler and May Street. The length of this section of Chandler Street is 0.52 miles, and the length of this section May Street is 0.1 miles. For this project there will be roadway alignment changes to the southerly intersection of Chandler and May to increase safety for all modes of traffic. This will increase sight distance for vehicles, reduce crossing times for pedestrians and provide a bike lane for cyclists. Improvements to the sidewalks and curbing will provide on street parking for the students of Worcester State University (WSU) and the parents of children at local schools. Flashing beacons will be used at critical crossing locations to increase safety of students and children. Islands will be installed in the roadway to reduce lane width and provide a landscape area. Street lighting will be improved to provide proper lighting to areas with crosswalks.
Location:
  • City of Worcester
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2025
    Project Manager: Joseph Gyujong Yoo
    Estimated Total Contract Cost: $5,453,208.96
    Estimated Total Federal Participating Construction Cost: $6,000,525.86
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: Design Public Hearing (as of 06/15/2022 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: WORCESTER
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, HSIP + CMAQ + STBG Total Project Cost = $6,000,526, Design Status = 25%, PM Score = 14 out of 27
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $1,600,000.00
    State Cost: $400,000.00
    Total Cost: $2,000,000.00

    Planned Federal FY: 2025
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: WORCESTER
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, HSIP + CMAQ + STBG Total Project Cost = $6,000,526, Design Status = 25%, PM Score = 14 out of 27
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $900,000.00
    State Cost: $100,000.00
    Total Cost: $1,000,000.00

    Planned Federal FY: 2025
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: WORCESTER
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, HSIP + CMAQ + STBG Total Project Cost = $6,000,526, Design Status = 25%, PM Score = 14 out of 27
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $2,400,420.80
    State Cost: $600,105.20
    Total Cost: $3,000,526.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/29/2017
    Project Need Form PNF Approved 11/27/2017
    Project Initiation Form PIF Entered 11/29/2017
    Project Initiation Form PIF Approved 11/29/2017
    Project Initiation Form PRC Submitted 12/08/2017
    Project Review Committee PRC Approved 12/14/2017
    Project Management
    25% Design 25% Package Received 09/15/2021
    25% Design 25% Package Comments to DE 12/27/2021
    25% Design Design Public Hearing 06/15/2022