Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 4- PAVEMENT PRESERVATION AT VARIOUS LOCATIONS
Location:
Construction Begins: Summer 2019
Resident Engineer: Honer Mohammed
Construction Bid Price: $995,920.20
District: District 4

Contracts (1) Progress
# 107114 -- Construction Contract
Crack Sealing, Pavement Repairs and Related Work at Various Locations Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/09/2019
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/30/2017
    Project Initiation Form PIF Entered 11/30/2017
    Project Initiation Form PRC Submitted 12/01/2017
    Project Review Committee PRC Approved 12/06/2017
    Project Status Advertised 02/23/2019
    Project Management
    Final Design PS&E Received 02/04/2019
    Final Design PS&E to FAPRO 02/12/2019