Project 608988
(Click here for a glossary of terms)
Project Description:
DISTRICT 4- FACILITY FENCE REPAIRS & UPGRADES
Location:
Construction Begins:
Spring 2019
Resident Engineer:
Christophen Dighton
Construction Bid Price:
$329,280.90
District:
District 4
Contracts
(1)
Progress
# 106345 -- Construction Contract
Fence Repairs and Replacements at Various Facilities and Rest Areas
Completed
Bridges
- none -
Construction Progress
Milestone Details
TIP/Funding
Project Issues
Contract Dates
Notice to Proceed:
06/13/2019
Contract Information
Project Designer:
In-House Boston
Funding Source:
Non Federal Aid
Construction Progress
Milestone Details
TIP/Funding
Project Issues
See the Milestone Details tab for additional Project information
Initiation
no comments
Scoping
no comments
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
Construction Progress
Milestone Details
TIP/Funding
Project Issues
TIP Lines for
2026 - 2030
No TIP Data Available For This Project
Construction Progress
Milestone Details
TIP/Funding
Project Issues
Project Task Information
Project Status
Project Need Form
PNF Entered
12/06/2017
Project Initiation Form
PIF Entered
12/06/2017
Project Initiation Form
PRC Submitted
12/06/2017
Project Review Committee
PRC Approved
12/14/2017
Project Status
Advertised
11/03/2018
Project Management
100% Design
100% Package Received
08/14/2018
Final Design
PS&E Received
10/22/2018
Final Design
PS&E to FAPRO
10/24/2018