DISTRICT 5- EXPANSION OF ITS ROADWAY EQUIPMENT FOR HIGHWAY OPERATIONS
Location:
Construction Begins: Spring 2019
Resident Engineer: Misael Sanchez
Construction Bid Price: $2,825,840.98
District: District 5

Contracts (1) Progress
# 105776 -- Construction Contract
Installation of an Intelligent Transportation System (ITS) (22 Closed Circuit Television Cameras, 2 Variable Message Signs, 4 Road Weather Information systems and 2 Traffic c 100% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/27/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/11/2017
    Project Initiation Form PIF Entered 12/11/2017
    Project Initiation Form PRC Submitted 12/11/2017
    Project Review Committee PRC Approved 12/14/2017
    Project Status Advertised 09/01/2018
    Project Management
    100% Design 100% Package Received 06/01/2018
    100% Design 100% Package Comments to DE 07/04/2018
    25% Design 25% Package Received 03/09/2018
    75% Design 75% Package Received 03/09/2018
    Final Design PS&E Received 08/14/2018
    Final Design PS&E to FAPRO 08/17/2018