Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 6- SCHEDULED & EMERGENCY GUARDRAIL & FENCE REFURBISHMENT & SNOW FENCE INSTALLATION AT VARIOUS LOCATIONS
Location:
Construction Begins: Summer 2019
Resident Engineer: Marc Sullivan
Construction Bid Price: $1,037,143.00
District: District 6

Contracts (1) Progress
# 106976 -- Construction Contract
Scheduled and Emergency Guardrail and Fence Repairs and Improvements at Various Locations Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/07/2019
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/31/2018
    Project Initiation Form PIF Entered 01/31/2018
    Project Initiation Form PRC Submitted 01/31/2018
    Project Review Committee PRC Approved 02/06/2018
    Project Status Advertised 02/02/2019
    Project Management
    100% Design 100% Package Received 11/29/2018
    Final Design PS&E Received 01/25/2019
    Final Design PS&E to FAPRO 01/29/2019