Project Description:
REHOBOTH- SOMERSET- SWANSEA- SYSTEMATIC BRIDGE PRESERVATION AT 10 BRIDGES ALONG THE I-195 CORRIDOR
Location:
  • Town of Rehoboth
  • Town of Somerset
  • Town of Swansea
  • Construction Begins: Winter 2022/2023
    Resident Engineer: Nelson Borges
    Construction Bid Price: $9,176,556.50
    District: District 5
    Current Status: Steel repairs, by Atlantic Bridge, currently awaiting response to an RFI. Bridge painting is underway and currently Lee’s River Ave. and Vinnicum are prepared for painting to begin. Scheduled work hours are Monday through Friday, 7:00 PM to 5:30 AM. Expect periodic lane closures and restrictions. (as of 03/14/2025)

    Contracts (1) Progress
    # 120928 -- Construction Contract
    Bridge Deck, Joint, and Substructure Repairs and Related Work (Including Painting) on 10 Bridges along Interstate 195 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/10/2023
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Steel repairs, by Atlantic Bridge, currently awaiting response to an RFI. Bridge painting is underway and currently Lee’s River Ave. and Vinnicum are prepared for painting to begin. Scheduled work hours are Monday through Friday, 7:00 PM to 5:30 AM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/06/2018
    Project Initiation Form PIF Entered 02/06/2018
    Project Initiation Form PRC Submitted 02/06/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Status Advertised 12/10/2022
    Project Management
    100% Design 100% Package Received 08/12/2022
    100% Design 100% Package Comments to DE 10/03/2022
    Final Design PS&E Received 10/20/2022
    Final Design PS&E Received - Resub 1 11/08/2022