Project Description:
TEWKSBURY- LOWELL- INTERSECTION IMPROVEMENTS AT ANDOVER STREET (ROUTE 133) AND RIVER ROAD
The proposed improvements include the installation of a fully-actuated traffic signal; re-alignment of the north and south intersection approaches; minor widening of Andover St to provide a 4-lane cross section west of the intersection, a 3-lane cross section east of the intersection, bicycle lanes and sidewalks on both sides; minor widening of River Rd to provide a 3-lane cross section with sidewalks on both sides; full-depth pavement reclaim of Andover St in Tewksbury; full-depth pavement reconstruction of Andover St in Lowell; mill and overlay of River Rd; removal of crosswalks and ADA ramps just north and west of the intersection; ADA compliant wheelchair ramps at the intersection; drainage upgrades/modifications, and MUTCD compliant signs and pavements markings. The improvements will extend approximately 1600’ along Andover Street and 500’ along River Road, and will be designed to meet the approval of MassDOT and the Town of Tewksbury. The work will also require coordination with the City of Lowell for the work along Andover Street that falls within their jurisdiction.
Location:
  • City of Lowell
  • Town of Tewksbury
  • Construction Begins: Summer 2020
    Resident Engineer: Benjamin McCarthy
    Construction Bid Price: $3,338,199.13
    District: District 4
    Current Status: Project has reached Full Beneficial Use. Minor surface work and punch list items remain, which will be completed this Spring. (as of 02/01/2024)

    Contracts (1) Progress
    # 111308 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at Andover Street (Route 133) and River Road 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/14/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Project has reached Full Beneficial Use. Minor surface work and punch list items remain, which will be completed this Spring.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/15/2018
    Project Need Form PNF Approved 01/05/2018
    Project Initiation Form PIF Entered 02/15/2018
    Project Initiation Form PIF Approved 02/15/2018
    Project Initiation Form PRC Submitted 02/15/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Status Advertised 05/09/2020
    Project Management
    100% Design 100% Package Received 10/16/2019
    25% Design 25% Package Received 06/06/2018
    25% Design 25% Package Comments to DE 08/03/2018
    25% Design Design Public Hearing 12/11/2018
    75% Design 75% Package Received 05/24/2019
    Final Design PS&E Received 01/22/2020
    Final Design PS&E Received - Resub 1 02/28/2020