Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
TEWKSBURY- LOWELL- INTERSECTION IMPROVEMENTS AT ANDOVER STREET (ROUTE 133) AND RIVER ROAD
Location:
  • City of Lowell
  • Town of Tewksbury
  • Construction Begins: Summer 2020
    Resident Engineer: Jay Patel
    Construction Bid Price: $3,338,199.13
    District: District 4
    Current Status: Sidewalk fine grading, compacting, and forming continues on Andover Street in Tewksbury, with the concrete sidewalk pour scheduled by the end of September. (as of 09/09/2021)
    Additional Info: National Grid Electric and Crown Castle utility relocation work is complete. AT&T and Comcast have been given a Notice to Proceed. (as of 09/09/2021)

    Contracts (1) Progress
    # 111308 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at Andover Street (Route 133) and River Road 27% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/14/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Sidewalk fine grading, compacting, and forming continues on Andover Street in Tewksbury, with the concrete sidewalk pour scheduled by the end of September.
    Additional Info
    National Grid Electric and Crown Castle utility relocation work is complete. AT&T and Comcast have been given a Notice to Proceed.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/15/2018
    Project Need Form PNF Approved 01/05/2018
    Project Initiation Form PIF Entered 02/15/2018
    Project Initiation Form PIF Approved 02/15/2018
    Project Initiation Form PRC Submitted 02/15/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Status Advertised 05/09/2020
    Project Management
    100% Design 100% Package Received 10/16/2019
    25% Design 25% Package Received 06/06/2018
    25% Design 25% Package Comments to DE 08/03/2018
    25% Design Design Public Hearing 12/11/2018
    75% Design 75% Package Received 05/24/2019
    Final Design PS&E Received 01/22/2020
    Final Design PS&E Received - Resub 1 02/28/2020