Project Description:
DISTRICT 5- HIGHWAY SWEEPING AT VARIOUS LOCATIONS
Location:
Construction Begins:
Summer 2019
Resident Engineer:
Joseph Martin
Construction Bid Price:
$1,234,567.53
District:
District 5
Contracts
(1)
Progress
# 107403 -- Construction Contract
Highway Sweeping at Various Locations (Excluding Martha's Vineyard and the Islands) (Re-Advertised Project)
Completed
Bridges
- none -
Construction Progress
Milestone Details
TIP/Funding
Project Issues
Contract Dates
Notice to Proceed:
08/28/2019
Contract Information
Project Designer:
In-House Boston
Funding Source:
Non Federal Aid
Construction Progress
Milestone Details
TIP/Funding
Project Issues
See the Milestone Details tab for additional Project information
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
Construction Progress
Milestone Details
TIP/Funding
Project Issues
TIP Lines for
2024 - 2028
No TIP Data Available For This Project
Construction Progress
Milestone Details
TIP/Funding
Project Issues
Project Task Information
Project Status
Project Need Form
PNF Entered
02/22/2018
Project Initiation Form
PIF Entered
02/22/2018
Project Initiation Form
PRC Submitted
02/22/2018
Project Review Committee
PRC Approved
02/27/2018
Project Status
Advertised
09/29/2018
Project Status
Advertised
04/06/2019
Project Management
100% Design
100% Package Received
08/31/2018
Final Design
PS&E Received
09/21/2018
Final Design
PS&E to FAPRO
09/24/2018