Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WEST BROOKFIELD- RESURFACING & RELATED WORK ON ROUTE 9, FROM 850' WEST OF WELCOME ROAD TO PIERCE ROAD (1 MILE - PHASE II)
Route 9 from 850 West of Welcome Road to Pierce Road (1 mile) will be widened to provide appropriate bicycle accommodation and resurfaced. Drainage improvements are proposed to remove stormwater runoff and snowmelt from the highway. Guardrail will be replaced as required and new signage and pavement markings will be included.
Location:
  • Town of West Brookfield
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2025
    Project Manager: Adam W Kiel
    Estimated Total Contract Cost: $8,100,107.78
    Estimated Total Federal Participating Construction Cost: $8,628,880.90
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 2
    Current Status: 100% Package Received (as of 03/12/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: WEST BROOKFIELD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $7,708,583, Design Status = 75%, YOE = 4%, PM Score = 11 out of 27
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $6,166,866.40
    State Cost: $1,541,716.60
    Total Cost: $7,708,583.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/27/2018
    Project Need Form PNF Approved 02/27/2018
    Project Initiation Form PIF Entered 02/27/2018
    Project Initiation Form PIF Approved 02/27/2018
    Project Initiation Form PRC Submitted 03/05/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Status Approved 25% 07/09/2020
    Project Management
    100% Design 100% Package Received 03/12/2024
    25% Design 25% Package Received 07/09/2020
    25% Design 25% Package Comments to DE 07/09/2020
    25% Design 25% Package Approved 07/09/2020
    25% Design Design Public Hearing 12/10/2020
    75% Design 75% Package Received 09/10/2021
    75% Design 75% Package Comments to DE 12/17/2021
    Consultant Contract Process NTP Issued 07/01/2011