Project Description:
WEST BROOKFIELD- RESURFACING & RELATED WORK ON ROUTE 9, FROM 850' WEST OF WELCOME ROAD TO PIERCE ROAD (1 MILE - PHASE II)
Route 9 from 850 West of Welcome Road to Pierce Road (1 mile) will be widened to provide appropriate bicycle accommodation and resurfaced. Drainage improvements are proposed to remove stormwater runoff and snowmelt from the highway. Guardrail will be replaced as required and new signage and pavement markings will be included.
Location:
  • Town of West Brookfield
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Project Manager: Adam W Kiel
    Estimated Total Federal Participating Construction Cost: N/A
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 2
    Current Status: Final Package to FAPRO (as of 03/28/2025 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Planned Federal FY: 2025
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: WEST BROOKFIELD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $8,628,881, Design Status = 100%, PM Score = 11 out of 27
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $6,903,104.80
    State Cost: $1,725,776.20
    Total Cost: $8,628,881.00

    Project Task Information
    Project Status
    Project Status Approved 25% 07/09/2020
    Project Status PIF Entered 02/27/2018
    Project Status PNF Entered 02/27/2018
    Project Status PIF Approved 02/27/2018
    Project Status PNF Approved 02/27/2018
    Project Status PRC Approved 03/15/2018
    Project Status PRC Submitted 03/05/2018
    Project Management
    Consultant Contract Process NTP Issued 07/01/2011
    Consultant Contract Process 25% Package Received 07/09/2020
    Consultant Contract Process 75% Package Received 09/10/2021
    Consultant Contract Process 100% Package Received 03/12/2024
    Consultant Contract Process PS&E Received 02/13/2025
    Consultant Contract Process 25% Package Comments to DE 07/09/2020
    Consultant Contract Process 75% Package Comments to DE 12/17/2021
    Consultant Contract Process 100% Package Comments to DE 04/16/2024
    Consultant Contract Process 25% Package Approved 07/09/2020
    Consultant Contract Process PS&E to FAPRO 03/28/2025
    Consultant Contract Process Design Public Hearing 12/10/2020