WEST BROOKFIELD- RESURFACING & RELATED WORK ON ROUTE 9, FROM 850' WEST OF WELCOME ROAD TO PIERCE ROAD (1 MILE - PHASE II)
Route 9 from 850 West of Welcome Road to Pierce Road (1 mile) will be widened to provide appropriate bicycle accommodation and resurfaced. Drainage improvements are proposed to remove stormwater runoff and snowmelt from the highway. Guardrail will be replaced as required and new signage and pavement markings will be included.
Location:
  • Town of West Brookfield
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Project Manager: Adam W Kiel
    Estimated Total Federal Participating Construction Cost: N/A
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 2
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Planned Federal FY: 2025
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: WEST BROOKFIELD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $8,628,881, Design Status = 100%, PM Score = 11 out of 27
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $6,903,104.80
    State Cost: $1,725,776.20
    Total Cost: $8,628,881.00