Project Description:
WEST BROOKFIELD- RESURFACING & RELATED WORK ON ROUTE 9, FROM 850' WEST OF WELCOME ROAD TO PIERCE ROAD (1 MILE - PHASE II)
Route 9 from 850 West of Welcome Road to Pierce Road (1 mile) will be widened to provide appropriate bicycle accommodation and resurfaced. Drainage improvements are proposed to remove stormwater runoff and snowmelt from the highway. Guardrail will be replaced as required and new signage and pavement markings will be included.
Location:
  • Town of West Brookfield
  • Construction Begins: Summer 2025
    Resident Engineer: Bailey Powers
    Construction Bid Price: $6,401,956.00
    District: District 2

    Contracts (1) Progress
    # 129976 -- Construction Contract
    Resurfacing & Related Work on Route 9, from 850' West of Welcome Road to Pierce Road (1 Mile - Phase II) 1% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/05/2025
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/27/2018
    Project Need Form PNF Approved 02/27/2018
    Project Initiation Form PIF Entered 02/27/2018
    Project Initiation Form PIF Approved 02/27/2018
    Project Initiation Form PRC Submitted 03/05/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Status Approved 25% 07/09/2020
    Project Status Advertised 04/12/2025
    Project Management
    100% Design 100% Package Received 03/12/2024
    100% Design 100% Package Comments to DE 04/16/2024
    25% Design 25% Package Received 07/09/2020
    25% Design 25% Package Comments to DE 07/09/2020
    25% Design 25% Package Approved 07/09/2020
    25% Design Design Public Hearing 12/10/2020
    75% Design 75% Package Received 09/10/2021
    75% Design 75% Package Comments to DE 12/17/2021
    Final Design PS&E Received 02/13/2025
    Final Design PS&E to FAPRO 03/28/2025
    Consultant Contract Process NTP Issued 07/01/2011