CANTON- DEDHAM- NORWOOD- HIGHWAY LIGHTING IMPROVEMENTS AT I-93 & I-95/128
Project scope includes the instillation of new high mast light poles with drill down lighting assemblies, replacement of all conduit, handholes and manholes in the system, replace existing lighting controller, cabinet and components, evaluate need to replace utility service, create safe access points for future maintenance.
Location:
  • Town of Canton
  • Town of Dedham
  • Town of Norwood
  • Construction Begins: Spring 2023
    Resident Engineer: Derek Coble
    Construction Bid Price: $3,594,225.75
    District: District 6

    Contracts (1) Progress
    # 121256 -- Construction Contract
    Highway Lighting Improvements and Related Work at the I-93 and I-95 Interchange 43% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 05/02/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/01/2018
    Project Need Form PNF Approved 03/01/2018
    Project Initiation Form PIF Entered 03/01/2018
    Project Initiation Form PIF Approved 03/01/2018
    Project Initiation Form PRC Submitted 03/01/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Status Advertised 01/28/2023
    Project Management
    100% Design 100% Package Received 11/30/2022
    25% Design 25% Package Received 02/08/2021
    25% Design 25% Package Comments to DE 03/30/2021
    75% Design 75% Package Received 06/22/2022
    75% Design 75% Package Comments to DE 08/01/2022
    Final Design PS&E Received 01/12/2023
    Final Design PS&E to FAPRO 01/13/2023