PEABODY TO GLOUCESTER- GUIDE AND TRAFFIC SIGN REPLACEMENT ON ROUTE 128
Replacement and upgrading of guide and traffic signs on Route 128 between Lowell Street in Peabody and Route 127 in Gloucester, including applicable signs on intersecting secondary roads.
Location:
  • City of Beverly
  • Town of Danvers
  • City of Gloucester
  • Town of Manchester By the sea
  • City of Peabody
  • Town of Wenham
  • Construction Begins: Spring 2024
    Resident Engineer: Mark Spinale
    Construction Bid Price: $1,689,147.00
    District: District 4

    Contracts (1) Progress
    # 125518 -- Construction Contract
    Guide and Traffic Sign Replacement on Route 128

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/21/2024
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/02/2018
    Project Initiation Form PIF Entered 03/02/2018
    Project Initiation Form PRC Submitted 03/02/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Status Advertised 03/16/2024
    Project Management
    100% Design 100% Package Received 09/26/2023
    100% Design 100% Package Comments to DE 12/08/2023
    25% Design 25% Package Received 11/29/2022
    25% Design 25% Package Comments to DE 01/24/2023
    25% Design 25% Package Approved 01/24/2023
    75% Design 75% Package Received 09/26/2023
    Final Design PS&E Received 01/24/2024
    Final Design PS&E to FAPRO 03/01/2024
    Consultant Contract Process Scope to DE 06/15/2021
    Consultant Contract Process NTP Issued 04/04/2022