Project Description:
PEABODY TO GLOUCESTER- GUIDE AND TRAFFIC SIGN REPLACEMENT ON ROUTE 128
Replacement and upgrading of guide and traffic signs on Route 128 between Lowell Street in Peabody and Route 127 in Gloucester, including applicable signs on intersecting secondary roads.
Location:
  • City of Beverly
  • Town of Danvers
  • City of Gloucester
  • Town of Manchester By the sea
  • City of Peabody
  • Town of Wenham
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2024
    Project Manager: Stephen Timmins
    Estimated Total Contract Cost: $2,542,007.50
    Estimated Total Federal Participating Construction Cost: $2,754,711.00
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: This project has been advertised for construction bids. (as of 03/16/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: District
    Districts: District 4
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • STIP Action #1. Increase from $1,714,693.00 to $2,297,503.
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $2,067,752.70
    State Cost: $229,750.30
    Total Cost: $2,297,503.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/02/2018
    Project Initiation Form PIF Entered 03/02/2018
    Project Initiation Form PRC Submitted 03/02/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Status Advertised 03/16/2024
    Project Management
    100% Design 100% Package Received 09/26/2023
    100% Design 100% Package Comments to DE 12/08/2023
    25% Design 25% Package Received 11/29/2022
    25% Design 25% Package Comments to DE 01/24/2023
    25% Design 25% Package Approved 01/24/2023
    75% Design 75% Package Received 09/26/2023
    Final Design PS&E Received 01/24/2024
    Final Design PS&E to FAPRO 03/01/2024
    Consultant Contract Process Scope to DE 06/15/2021
    Consultant Contract Process NTP Issued 04/04/2022