Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
LYNNFIELD- PEABODY- DANVERS- GUIDE AND TRAFFIC SIGN REPLACEMENT ON I-95/128 (TASK 'A' INTERCHANGE)
The project will consist of the updating and replacement of guide and traffic signs on Interstate 95 between Lynnfield and Danvers for the Route 128 interchange - aka the Task 'A' interchange - in Peabody, including applicable signing on intersecting roadways.
Location:
  • Town of Danvers
  • Town of Lynnfield
  • City of Peabody
  • Construction Begins: Spring 2022
    Resident Engineer: Anthony Neve
    Construction Bid Price: $629,834.80
    District: District 4
    Current Status: Contract work is complete. (as of 12/07/2023)

    Contracts (1) Progress
    # 117604 -- Construction Contract
    Guide and Traffic Sign Replacement along a Section of Interstate 95 and Route 128 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/02/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Contract work is complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/05/2018
    Project Initiation Form PIF Entered 03/05/2018
    Project Initiation Form PRC Submitted 03/05/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Status Advertised 03/19/2022
    Project Management
    100% Design 100% Package Received 10/25/2021
    100% Design 100% Package Comments to DE 12/13/2021
    25% Design 25% Package Received 05/28/2021
    25% Design 25% Package Comments to DE 08/10/2021
    25% Design 25% Package Approved 08/10/2021
    75% Design 75% Package Received 10/25/2021
    Final Design PS&E Received 01/24/2022
    Final Design PS&E to FAPRO 03/03/2022