Project Description:
WORCESTER- LEOMINSTER- GUIDE AND TRAFFIC SIGN REPLACEMENT ON INTERSTATE 190
Location:
  • City of Leominster
  • City of Worcester
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2022/2023
    Project Manager: Stephen Timmins
    Estimated Total Contract Cost: $3,829,254.90
    Estimated Total Federal Participating Construction Cost: $4,160,690.80
    Funding Provision: This project is planned to be funded through the 2023 Transportation Improvement Program for the STATEWIDE.
    District: District 3
    Current Status: PS&E Received (as of 02/26/2021 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2023
    Responsible MPO: STATEWIDE
    Location: Municipality
    Cities: LEOMINSTER
    WORCESTER
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $3,044,051.10
    State Cost: $338,227.90
    Total Cost: $3,382,279.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/05/2018
    Project Initiation Form PIF Entered 03/05/2018
    Project Initiation Form PRC Submitted 03/05/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Management
    100% Design 100% Package Received 08/10/2020
    75% Design 75% Package Received 08/10/2020
    Final Design PS&E Received 02/26/2021