Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WAREHAM TO BOURNE- GUIDE AND TRAFFIC SIGN REPLACEMENT ON ROUTE 25
Location:
  • Town of Bourne
  • Town of Wareham
  • Construction Begins: Spring 2023
    Resident Engineer: Zachary Kelley
    Construction Bid Price: $698,199.50
    District: District 5
    Current Status: The contractor is currently fabricating overhead signs and sign supports. The contractor is installing ground mounted signs along Rte. 25. The Contractor will be utilizing the MUTCD approved traffic safety setup for right shoulder closure. The Roadway will remain open at all times.Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 04/02/2024)

    Contracts (1) Progress
    # 121257 -- Construction Contract
    Fabrication, Installation and Replacement of Overhead and Ground Mounted Guide and Traffic Signs along a Section of Route 25

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/24/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/05/2018
    Project Initiation Form PIF Entered 03/05/2018
    Project Initiation Form PRC Submitted 03/05/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Status Advertised 01/28/2023
    Project Management
    100% Design 100% Package Received 04/05/2022
    100% Design 100% Package Comments to DE 06/24/2022
    75% Design 75% Package Received 04/05/2022
    Final Design PS&E Received 09/27/2022
    Final Design PS&E to FAPRO 01/13/2023
    Consultant Contract Process Scope to DE 04/12/2021
    Consultant Contract Process NTP Issued 04/26/2021