Project Description:
HOLYOKE- RESURFACING AND RELATED WORK ON CABOT STREET AND RACE STREET (CENTER CITY CONNECTOR)
The proposed project limits extend along Race Street (Appleton Street to Cabot Street, approx. 1,000-linear feet) and along Cabot Street (Race Street to the Willimansett Bridge, approx. 2,000-linear feet). On Race Street, the project included the rehabilitation of pavement (mill and overlay), new sidewalks, on-street parking, and a connection to the Phase II Canal Walk. On Cabot Street, the project includes the rehabilitation of pavement (mill and overlay), new sidewalks, and minor roadway widening to accommodate two 11-foot travel lanes, 5-foot shoulders for bicycle accommodates, and 7-foot wide parallel parking spaces on both sides of roadway. Two traffic signals are proposed to be upgraded, Main Street at Cabot Street and Cabot Street at South Canal Street. Finally, there is a bridge over the third level canal (between South Canal Street and the Willimansett Bridge) that is owned by MassDOT where the sidewalks and the parapet walls will be repaired and/ or replaced with a moment slab sidewalk/ wall combination. There are jersey barriers currently present on the easterly side of the bridge. This bridge is known as the Cabot Street Bridge (H-21-008).
Location:
  • City of Holyoke
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2025
    Project Manager: Janhavi Limaye
    Estimated Total Contract Cost: $6,865,303.52
    Estimated Total Federal Participating Construction Cost: $5,493,366.09
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: 75% Package Comments to DE (as of 07/05/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: HOLYOKE
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction (YOE $5,308,293) TEC 54.5 / 25% STBG
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $4,570,480.80
    State Cost: $1,142,620.20
    Total Cost: $5,713,101.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/06/2018
    Project Need Form PNF Approved 02/28/2018
    Project Initiation Form PIF Entered 03/06/2018
    Project Initiation Form PIF Approved 03/06/2018
    Project Initiation Form PRC Submitted 03/06/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Management
    25% Design 25% Package Received 01/29/2020
    25% Design Design Public Hearing 11/10/2021
    75% Design 75% Package Received 04/04/2023
    75% Design 75% Package Comments to DE 07/05/2023