Project Description:
NEWTON- WESTON- MULTI-USE TRAIL CONNECTION, FROM RECREATION ROAD TO UPPER CHARLES RIVER GREENWAY INCLUDING RECONSTRUCTION OF PED BRIDGE N-12-078=W-29-062
This project includes replacement of the pedestrian bridge over the Charles River and connecting pathways on the east side of the bridge to connect to Riverside Road, Charles Street, and / or Oakland Avenue and bike / pedestrian accommodations on local streets. Project may also include on-street or at-grade crossing bike / pedestrian improvements.
Location:
  • City of Newton
  • Town of Weston
  • Construction Begins: Autumn 2022
    Resident Engineer: Jeffrey Macioce
    Construction Bid Price: $4,244,557.50
    District: District 6

    Contracts (2) Progress
    # 120177 -- Construction Contract
    Pedestrian Bridge Replacement Br. No. N-12-078=W-29-062 (Prefabricated Steel Truss) Riverside and Recreation Roads over the Charles River 61% Complete
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 11/03/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/06/2018
    Project Need Form PNF Approved 02/16/2018
    Project Initiation Form PIF Entered 03/06/2018
    Project Initiation Form PIF Approved 03/06/2018
    Project Initiation Form PRC Submitted 03/09/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Status Advertised 09/10/2022
    Project Management
    100% Design 100% Package Received 03/17/2021
    100% Design 100% Package Comments to DE 04/28/2021
    25% Design 25% Package Received 12/21/2018
    25% Design 25% Package Comments to DE 03/05/2019
    25% Design 25% Package Approved 10/15/2019
    25% Design 25% Package Received - Resub 1 07/26/2019
    25% Design Design Public Hearing 12/11/2019
    75% Design 75% Package Received 07/17/2020
    75% Design 75% Package Comments to DE 11/01/2020
    Final Design PS&E Received 09/13/2021
    Final Design PS&E Received - Resub 1 12/22/2021
    Final Design PS&E Received - Resub 2 03/23/2022
    Final Design PS&E Received - Resub 3 05/03/2022
    Final Design PS&E Received - Resub 4 06/10/2022
    Consultant Contract Process NTP Issued 06/13/2018