Project Description:
BARNSTABLE- CONSTRUCTION OF A SHARED USE PATH ALONG BEARSES WAY, FROM ROUTE 28 TO PITCHERS WAY
Construct a new paved bicycle/pedestrian shared-use path along a grassed/wooded area on the west side of Bearse’s Way, from the DPW south drive to Pitcher’s Way, a distance of 3802 feet or .72 miles. The paved width of the path will be 10 feet and 3-foot unpaved stabilized shoulders will be provided on each side with slopes no greater than 6:1 horizontal to vertical. Utilities will be relocated if necessary. Drainage will be improved as necessary/appropriate. Lighting will be installed through wooded areas; open areas are lit by existing street lights. Arborvitae will be planted along the DPW chain link fence for visual screening and a safety buffer. A crosswalk and ADA-compliant sidewalk ramps will be installed across Pitcher’s Way at Bearse’s Way. The shared-use path terminus at Pitcher’s Way will include a splitter channel to prevent vehicle access.
Location:
  • Town of Barnstable
  • Construction Begins: Winter 2023/2024
    Resident Engineer: Zachary Kelley
    Construction Bid Price: $4,034,933.03
    District: District 5
    Current Status: The contractor is working on off-road gravity sewer installation. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 01/13/2025)

    Contracts (1) Progress
    # 124017 -- Construction Contract
    Construction of a Shared Use Path along Bearses Way, from Route 28 to Pitchers Way 10% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/26/2023
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    The contractor is working on off-road gravity sewer installation. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/06/2018
    Project Need Form PNF Approved 02/16/2018
    Project Initiation Form PIF Entered 03/06/2018
    Project Initiation Form PIF Approved 03/06/2018
    Project Initiation Form PRC Submitted 03/12/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Status Advertised 09/09/2023
    Project Management
    100% Design 100% Package Received 02/01/2023
    25% Design 25% Package Received 07/12/2018
    25% Design 25% Package Comments to DE 11/08/2018
    25% Design Design Public Hearing 10/26/2020
    75% Design 75% Package Received 03/17/2021
    75% Design 75% Package Comments to DE 07/16/2021
    Final Design PS&E Received - Resub 1 06/27/2023