Project Description:
SHEFFIELD- BRIDGE REPLACEMENT, S-10-015, KELSEY ROAD OVER SCHENOB BROOK
The recommended bridge replacement entails a superstructure with an increased hydraulic opening measuring approximately 70 feet in length and 16 feet in width. The superstructure comprises four adjacent prestressed concrete box beams supported by full-height concrete cantilever abutments with pile foundations and U-wing walls. Riprap will be installed along the entire channel of Schenob Brook beneath the bridge. The bridge and approach slabs will be paved with an asphalt riding surface, while the remainder of Kelsey Road will retain its existing gravel riding surface. The proposed roadway cross section will consist of a single lane, measuring 13 feet in width, featuring a crown at the center and 2% cross slopes. Guiderails will be installed on both sides of the roadway along each bridge approach.
Location:
  • Town of Sheffield
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2026
    Project Manager: Joshua Bartus
    Estimated Total Contract Cost: $3,868,541.27
    Estimated Total Federal Participating Construction Cost: $4,187,200.21
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: 25% Package Received - Resub 2 (as of 10/08/2024 )

    Contracts (2) Progress
    # 115761 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77860 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: SHEFFIELD
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $3,483,709.60
    State Cost: $870,927.40
    Total Cost: $4,354,637.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/07/2018
    Project Need Form PNF Approved 03/07/2018
    Project Initiation Form PIF Entered 03/07/2018
    Project Initiation Form PIF Approved 03/07/2018
    Project Initiation Form PRC Submitted 03/07/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Management
    25% Design 25% Package Received 06/22/2023
    25% Design 25% Package Comments to DE 09/22/2023
    25% Design 25% Package Received - Resub 1 01/19/2024
    25% Design 25% Package Received - Resub 2 10/08/2024