GREAT BARRINGTON- BRIDGE REPLACEMENT, G-11-006, COTTAGE STREET OVER HOUSATONIC RIVER
Location:
  • Town of Great Barrington
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2026/2027
    Project Manager: Courtney Sulerud
    Estimated Total Contract Cost: $3,850,010.00
    Estimated Total Federal Participating Construction Cost: $4,200,011.00
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 01/14/2021 )

    Contracts (2) Progress
    # 77853 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77879 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: GREAT BARRINGTON
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $3,494,408.80
    State Cost: $873,602.20
    Total Cost: $4,368,011.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/07/2018
    Project Need Form PNF Approved 03/07/2018
    Project Initiation Form PIF Entered 03/07/2018
    Project Initiation Form PIF Approved 03/07/2018
    Project Initiation Form PRC Submitted 03/07/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Management
    Consultant Contract Process NTP Issued 01/14/2021