Project Description: |
GREAT BARRINGTON- BRIDGE REPLACEMENT, G-11-006, COTTAGE STREET OVER HOUSATONIC RIVER
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | Municipality |
Construction Begins: | Winter 2026/2027 |
Project Manager: | Courtney Sulerud |
Estimated Total Contract Cost: | $3,850,010.00 |
Estimated Total Federal Participating Construction Cost: | $4,200,011.00 |
Funding Provision: | This project is planned to be funded through the 2026 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization. |
District: | District 1 |
Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 01/14/2021 ) |
|