Project Description:
NEW MARLBOROUGH- BRIDGE REPLACEMENT, N-08-020, KEYES HILL ROAD OVER UMPACHENE RIVER
The proposed project consists of the replacement of an existing one-span, multi-steel beam superstructure supported on gravity concrete masonry abutments and wingwalls. The existing bridge span length is 42’-2” center to center bearings. The bridge carries one 14-foot lane of traffic but is used for 2-way direction. The project will reconstruct full depth highway pavement, construct highway guardrail transition, and replace highway guardrails. In addition, the improvement will consist of converting the 14-foot lane to two 9-foot lanes. This change will not modify the roadway geometry in horizontal alignment but little vertical profile adjustment, roadway alignment will remain the same as the existing. Pedestrian and bicycle accommodations will not be part of the project. A detour will be required during the construction.
Location:
  • Town of New Marlborough
  • Construction Begins: Winter 2024/2025
    Resident Engineer: Amelia LePrevost
    Construction Bid Price: $4,132,649.00
    District: District 1

    Contracts (2) Progress
    # 128111 -- Construction Contract
    Bridge Replacement, N-08-020, Keyes Hill Road Over Umpachene River
    # 77872 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 01/16/2025
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/07/2018
    Project Need Form PNF Approved 03/07/2018
    Project Initiation Form PIF Entered 03/07/2018
    Project Initiation Form PIF Approved 03/07/2018
    Project Initiation Form PRC Submitted 03/07/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Status Advertised 09/14/2024
    Project Management
    25% Design 25% Package Received 10/28/2021
    25% Design 25% Package Received 09/08/2023
    25% Design 25% Package Comments to DE 12/31/2021
    25% Design 25% Package Approved 01/31/2022
    25% Design Design Public Hearing 02/15/2022
    75% Design 75% Package Received 03/15/2024
    Final Design PS&E Received 06/14/2024
    Final Design PS&E to FAPRO 09/04/2024