Project Description:
BOSTON- MILTON- QUINCY- HIGHWAY LIGHTING SYSTEM REPLACEMENT ON I-93, FROM NEPONSET AVENUE TO THE BRAINTREE SPLIT
This project will replace the existing non-functional lighting system and will include new lighting poles, luminaires and foundations as well as new conduit runs and load centers.
Location:
  • City of Boston
  • Town of Milton
  • City of Quincy
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Ranjit Sivasubramaniam
    Estimated Total Contract Cost: $12,425,112.97
    Estimated Total Federal Participating Construction Cost: $12,860,990.11
    District: District 6
    Current Status: PS&E Received (as of 06/27/2022 )

    Contracts (1) Progress
    # 77878 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/09/2018
    Project Initiation Form PIF Entered 03/09/2018
    Project Initiation Form PRC Submitted 03/09/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Management
    100% Design 100% Package Received 03/18/2022
    25% Design 25% Package Received 11/06/2020
    75% Design 75% Package Received 07/19/2021
    75% Design 75% Package Comments to DE 09/03/2021
    Final Design PS&E Received 06/27/2022