Project Description:
BLACKSTONE- BLACKSTONE RIVER BIKEWAY RAILTRAIL CONSTRUCTION (PHASE 1, SEGMENT 2)
The project is Segment 1/ Phase 2 of the Blackstone River Greenway. This 0.45 mile segment will extend the Phase 1 segment from the St. Paul Street bridge (B-13-007) in Blackstone to the Massachusetts/ RI border. The proposed Greenway will be a 10 foot paved path with 2 foot shoulders, drainage swales, as needed. Railings and landscaping will be constructed as needed. A spur will be constructed near the existing Blackstone River levee to provide a lookout area over the Blackstone River. Two viaducts will require rehabilitation as a part of the project. Bridge No. B-13-027 which is a seven span concrete stone masonry viaduct and Bridge B-13-031 a single-span concrete and stone masonry arch viaduct. Due to poor drainage, both viaducts require repairs to correct the concrete facades, and the top area.
Location:
  • Town of Blackstone
  • Design Responsibility: Other
    Right of Way Responsibility: Other
    Project Manager: Michael Trepanier
    Estimated Total Contract Cost: $9,721,659.20
    Estimated Total Federal Participating Construction Cost: $10,163,552.80
    District: District 3
    Current Status: 100% Package Comments to DE (as of 06/28/2019 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/09/2018
    Project Need Form PNF Approved 03/09/2018
    Project Initiation Form PIF Entered 03/09/2018
    Project Initiation Form PIF Approved 03/09/2018
    Project Initiation Form PRC Submitted 03/09/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Management
    100% Design 100% Package Received 05/28/2019
    100% Design 100% Package Comments to DE 06/28/2019