WELLFLEET- PAVEMENT PRESERVATION AND RELATED WORK ON ROUTE 6
This project consists of pavement milling, resurfacing, and restriping of the hot mix asphalt pavement along Route 6 (Rt. 6) in Wellfleet from just north of Oakwood Lane near the Eastham/Wellfleet town line (MM 96.8±) to the MassDOT Main Street Improvement Project No. 607397 southern limits near Way 68 and just north of Cove Rd (MM 104.0±). The total length of this project is approximately 5.0 miles. The work on the Rt. 6 pavement preservation project will consist of pavement milling, resurfacing, re-striping including buffered bike lanes and crosswalks, new pedestrian crossing signals near Wellfleet Cinemas, at Marconi Beach Road, near Old County Road, and near Cove Road. Full traffic signal upgrades are proposed at the Marconi Beach Road intersection. In addition, new centerline rumble-strip, application of new pavement markings, guardrail replacement, new curb, sidewalk, and accessible ramps where bus stops are being improved, traffic management, clearing and grubbing, drainage improvements including adjustments and modifications such as but not limited to new structures, structure change in types, structure remodels, pipe work, and pipe and structure clean-out. Work will also include limited utility relocations, landscaping near the bus stops being improved, and other related work.
Location:
  • Town of Wellfleet
  • Construction Begins: Autumn 2023
    Resident Engineer: Ian Bettencourt
    Construction Bid Price: $15,181,230.50
    District: District 5
    Current Status: •Lawrence Lynch continues drainage work on Route 6 EB from Eastham toward Main St. Normal Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 04/18/2024)

    Contracts (2) Progress
    # 115791 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 124020 -- Construction Contract
    Pavement Preservation and Related Work on Route 6 5% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/01/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    •Lawrence Lynch continues drainage work on Route 6 EB from Eastham toward Main St. Normal Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/12/2018
    Project Need Form PNF Approved 03/12/2018
    Project Initiation Form PIF Entered 03/12/2018
    Project Initiation Form PIF Approved 03/12/2018
    Project Initiation Form PRC Submitted 03/12/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Status Advertised 09/09/2023
    Project Management
    100% Design 100% Package Received 05/08/2023
    100% Design 100% Package Comments to DE 06/13/2023
    25% Design 25% Package Received 05/29/2020
    25% Design 25% Package Comments to DE 09/03/2020
    25% Design Design Public Hearing 09/22/2021
    75% Design 75% Package Received 02/21/2022
    75% Design 75% Package Comments to DE 04/05/2022
    Final Design PS&E Received 08/15/2023
    Final Design PS&E Received - Resub 1 08/27/2023