Project Description:
GLOUCESTER- ESSEX- MANCHESTER-BY-THE-SEA- WENHAM- PAVEMENT PRESERVATION AND RELATED WORK ON ROUTE 128
Location:
  • Town of Essex
  • City of Gloucester
  • Town of Manchester By the sea
  • Town of Wenham
  • Construction Begins: Winter 2020/2021
    Resident Engineer: Anthony Lapensee
    Construction Bid Price: $14,831,201.91
    Funding Provision: This project is planned to be funded through the 2021 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: Work in progress: Mainline guardrail replacement, applying milling mulch on the roadway shoulders, bridge deck repairs on Bridge G-05-022 (Route 128 over Marsh street), adjusting and rebuilding drainage structures, replacing drainage covers and grates with lockdown covers/grates, and mainline milling. (as of 08/05/2021)

    Contracts (2) Progress
    # 113398 -- Construction Contract
    Resurfacing and Related Work (Including 8 Bridges and Ramps) along a Section of Route 128
    # 86785 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 4. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/09/2021
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Work in progress: Mainline guardrail replacement, applying milling mulch on the roadway shoulders, bridge deck repairs on Bridge G-05-022 (Route 128 over Marsh street), adjusting and rebuilding drainage structures, replacing drainage covers and grates with lockdown covers/grates, and mainline milling.
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2021
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: ESSEX
    GLOUCESTER
    MANCHESTER BY THE SEA
    WENHAM
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $11,914,340.80
    State Cost: $2,978,585.20
    Total Cost: $14,892,926.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/12/2018
    Project Need Form PNF Approved 03/12/2018
    Project Initiation Form PIF Entered 03/12/2018
    Project Initiation Form PIF Approved 03/12/2018
    Project Initiation Form PRC Submitted 03/12/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Status Advertised 10/31/2020
    Project Management
    100% Design 100% Package Received 07/03/2020
    25% Design 25% Package Received 02/21/2020
    25% Design 25% Package Comments to DE 03/26/2020
    75% Design 75% Package Received 02/21/2020
    75% Design 75% Package Comments to DE 03/26/2020
    Final Design PS&E Received 07/03/2020
    Final Design PS&E Received - Resub 1 10/02/2020