FLORIDA- NORTH ADAMS- RESURFACING AND RELATED WORK ON ROUTE 2
Location:
  • Town of Clarksburg
  • Town of Florida
  • City of North Adams
  • Construction Begins: Summer 2022
    Resident Engineer: Christopher Dindio
    Construction Bid Price: $5,814,908.69
    Funding Provision: This project is planned to be funded through the 2022 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1

    Contracts (1) Progress
    # 117951 -- Construction Contract
    Resurfacing and Related Work on a Section of Route 2 (Mohawk Trail)

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/01/2022
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2022
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: CLARKSBURG
    FLORIDA
    NORTH ADAMS
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $5,440,814.40
    State Cost: $1,360,203.60
    Total Cost: $6,801,018.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/12/2018
    Project Need Form PNF Approved 03/12/2018
    Project Initiation Form PIF Entered 03/12/2018
    Project Initiation Form PIF Approved 03/12/2018
    Project Initiation Form PRC Submitted 03/12/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Status Advertised 05/07/2022
    Project Management
    100% Design 100% Package Received 01/26/2022
    25% Design 25% Package Received 09/24/2021
    75% Design 75% Package Received 09/24/2021
    75% Design 75% Package Comments to DE 11/02/2021
    Final Design PS&E Received 01/26/2022
    Final Design PS&E to FAPRO 04/25/2022