Project Description:
PHILLIPSTON- TEMPLETON- PAVEMENT PRESERVATION AND RELATED WORK ON ROUTE 2
Location:
  • Town of Phillipston
  • Town of Templeton
  • Construction Begins: Winter 2022/2023
    Resident Engineer: Victor LaMountain
    Construction Bid Price: $9,832,427.68
    District: District 2

    Contracts (1) Progress
    # 120707 -- Construction Contract
    Resurfacing and Related Work on a Section of Route 2 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/26/2023
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/12/2018
    Project Need Form PNF Approved 03/12/2018
    Project Initiation Form PIF Entered 03/12/2018
    Project Initiation Form PIF Approved 03/12/2018
    Project Initiation Form PRC Submitted 03/12/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Status Advertised 11/05/2022
    Project Management
    100% Design 100% Package Received 01/24/2022
    25% Design 25% Package Received 07/16/2020
    25% Design 25% Package Received 07/16/2020
    75% Design 75% Package Received 07/16/2020
    75% Design 75% Package Comments to DE 10/29/2020
    Final Design PS&E Received 01/24/2022
    Final Design PS&E Received - Resub 1 07/07/2022