Project Description:
PHILLIPSTON- TEMPLETON- PAVEMENT PRESERVATION AND RELATED WORK ON ROUTE 2
Location:
  • Town of Phillipston
  • Town of Templeton
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2023/2024
    Project Manager: Haider Hamandi
    Estimated Total Contract Cost: $9,530,346.80
    Estimated Total Federal Participating Construction Cost: $9,701,431.20
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Montachusett Metropolitan Planning Organization.
    District: District 2
    Current Status: 75% Package Comments to DE (as of 10/29/2020 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Montachusett Metropolitan Planning Organization
    Location: Municipality
    Cities: PHILLIPSTON
    TEMPLETON
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $8,382,035.20
    State Cost: $2,095,508.80
    Total Cost: $10,477,544.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/12/2018
    Project Need Form PNF Approved 03/12/2018
    Project Initiation Form PIF Entered 03/12/2018
    Project Initiation Form PIF Approved 03/12/2018
    Project Initiation Form PRC Submitted 03/12/2018
    Project Review Committee PRC Approved 03/15/2018
    Project Management
    25% Design 25% Package Received 07/16/2020
    25% Design 25% Package Received 07/16/2020
    75% Design 75% Package Received 07/16/2020
    75% Design 75% Package Comments to DE 10/29/2020