Project Description:
GARDNER- BIKE PATH BRIDGE CONSTRUCTION, NORTH CENTRAL PATHWAY OVER ROUTE 140
The project involves construction of a bike path bridge over Route 140. The new bridge is along a modified alignment of the North Central Pathway. The new bridge will provide a grade separated crossing, linking the existing bike path to a section of bike path to be built on a utility easement by the City. When this segment is completed it will provide full connection between downtown Gardner and the center of Westminster. It will provide off-road access to the Crystal Lake recreation area, Henry Heywood Memorial Hospital, the District Court, the Gardner Middle and High Schools and Mount Wachusett Community College.
Location:
  • City of Gardner
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2027
    Project Manager: Joseph Gyujong Yoo
    Estimated Total Contract Cost: $7,160,414.23
    Estimated Total Federal Participating Construction Cost: $7,397,688.03
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Montachusett Metropolitan Planning Organization.
    District: District 3
    Current Status: Design Public Hearing (as of 04/25/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Montachusett Metropolitan Planning Organization
    Location: Municipality
    Cities: GARDNER
    Category: Advertised Projects Constr.
    Budget Section: 2C
    Advance Construct: No
    Air Quality Exempt: No

  • CMAQ
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $6,628,328.80
    State Cost: $1,657,082.20
    Total Cost: $8,285,411.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/15/2018
    Project Need Form PNF Approved 03/15/2018
    Project Initiation Form PIF Entered 03/15/2018
    Project Initiation Form PIF Approved 03/15/2018
    Project Initiation Form PRC Submitted 03/15/2018
    Project Review Committee Received 02/12/2021
    Project Review Committee PRC Approved 06/04/2018
    Project Management
    25% Design 25% Package Received 03/18/2022
    25% Design 25% Package Comments to DE 06/22/2022
    25% Design 25% Package Approved 10/25/2022
    25% Design Design Public Hearing 04/25/2023