Project Description:
BOSTON- MILTON- QUINCY- SOUTHEAST EXPRESSWAY/INTERSTATE 93 REPLACEMENT OF BARRIERS FOR HIGH OCCUPANCY VEHICLE LANE (HOV)
Project consists of the purchase of MASH compliant moveable concrete barrier for the HOV lane on I-93. (Installation by MassDOT personnel to be determined)
Location:
  • City of Boston
  • Town of Milton
  • City of Quincy
  • Construction Begins: Summer 2022
    Resident Engineer: Nicholas Renaud
    Construction Bid Price: $29,962,271.00
    District: District 6

    Contracts (1) Progress
    # 117901 -- Construction Contract
    Replacement of Barriers for the High Occupancy Vehicle (HOV) Lane on the Southeast Expressway-Interstate 93 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/10/2022
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/21/2018
    Project Initiation Form PIF Entered 03/21/2018
    Project Initiation Form PRC Submitted 03/21/2018
    Project Review Committee PRC Approved 03/22/2018
    Project Status Advertised 04/30/2022
    Project Management
    100% Design 100% Package Received 01/03/2022
    100% Design 100% Package Comments to DE 02/04/2022
    Final Design PS&E Received 02/24/2022
    Final Design PS&E Received - Resub 1 03/23/2022