Project Description:
BOSTON- LIGHTING REPAIRS IN THE I-93 TUNNEL (CRC 17D & 17F)
Location:
  • City of Boston
  • Construction Begins: Summer 2020
    Resident Engineer: Le Truong
    Construction Bid Price: $32,242,368.50
    District: District 6

    Contracts (2) Progress
    # 110219 -- Construction Contract
    Lighting Repairs and Improvements in the Central Artery Tunnel (I-93) (CRC 17D and 17F) Completed
    # 77857 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/04/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/22/2018
    Project Initiation Form PIF Entered 03/22/2018
    Project Initiation Form PRC Submitted 03/22/2018
    Project Review Committee PRC Approved 03/22/2018
    Project Status Advertised 11/23/2019
    Project Management
    100% Design 100% Package Received 08/23/2019
    25% Design 25% Package Received 03/01/2019
    Final Design PS&E Received 10/25/2019
    Final Design PS&E to FAPRO 11/13/2019