Project Description:
BOSTON- I-90 & MBTA PRUDENTIAL TUNNEL REHABILITATION
Work consists of installation of jet fans, backup power, lighting, fire standpipes, and communication equipment.
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: Other
    Project Manager: Steven E McLaughlin
    Estimated Total Contract Cost: $57,151,892.15
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: 100% Package Received - Resub 1 (as of 05/20/2020 )

    Contracts (2) Progress
    # 60493 -- Non-system contract type
    Statewide - Owner's Representative will perform peer reviews and manage cost recovery and value engineering for various projects
    # 80651 -- Non-system contract type
    Statewide - Owner's Representative will perform peer reviews and manage cost recovery and value engineering

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/22/2018
    Project Initiation Form PIF Entered 03/22/2018
    Project Initiation Form PIF Entered 03/22/2019
    Project Initiation Form PRC Submitted 07/12/2018
    Project Initiation Form PRC Submitted 03/22/2019
    Project Review Committee PRC Tabled 12/06/2018
    Project Review Committee PRC Approved 03/21/2019
    Project Management
    100% Design 100% Package Received 12/11/2018
    100% Design 100% Package Received - Resub 1 05/20/2020
    75% Design 75% Package Received 05/14/2018
    75% Design 75% Package Received - Resub 1 07/24/2018