Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NORTH ADAMS- SYSTEMATIC BRIDGE MAINTENANCE, N-14-017, ROUTE 2 OVER HOOSIC RIVER
Location:
  • City of North Adams
  • Construction Begins: Winter 2020/2021
    Resident Engineer: Peter Lamarre
    Construction Bid Price: $699,247.15
    Funding Provision: This project is planned to be funded through the 2021 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1

    Contracts (1) Progress
    # 113450 -- Construction Contract
    Bridge Deck Repairs and Related Work Br. No. N-14-017 Route 2 over the Hoosic River. 75% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 02/09/2021
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2021
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: NORTH ADAMS
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge
    Federal Cost: $417,760.00
    State Cost: $104,440.00
    Total Cost: $522,200.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/18/2018
    Project Need Form PNF Approved 04/18/2018
    Project Initiation Form PIF Entered 04/18/2018
    Project Initiation Form PIF Approved 04/18/2018
    Project Initiation Form PRC Submitted 04/18/2018
    Project Review Committee PRC Approved 07/19/2018
    Project Status Advertised 11/07/2020
    Project Management
    100% Design 100% Package Received 04/27/2020
    100% Design 100% Package Comments to DE 05/27/2020
    Final Design PS&E Received 06/09/2020
    Final Design PS&E Received - Resub 1 07/25/2020
    Final Design PS&E Received - Resub 2 09/10/2020