Project Description:
ATTLEBORO- BRIDGE WIDENING, A-16-052, AND BRIDGE REMOVAL, A-16-062, I-295 RAMP OVER TEN MILE RIVER
The project will consist of removal of existing ramp Interstate 295 over Ten Mile River, and construction of a replacement ramp/structure.
Location:
  • City of Attleboro
  • Construction Begins: Autumn 2023
    Resident Engineer: Eric Borman
    Construction Bid Price: $4,757,114.60
    District: District 5
    Current Status: JRC: Phase II installing loam at INF-2, excavation and subgrade for I-95 box widening. Scheduled work hours are Monday through Friday, 7:00 AM to 3:30 PM. (as of 03/13/2025)
    Additional Info: I-95 SB restricted from 3 lanes to 2 lanes as per Phase III TMP within the construction zone. All operations occurring behind barrier. (as of 03/13/2025)

    Contracts (3) Progress
    # 115801 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 123876 -- Construction Contract
    Bridge Widening, A-16-052 and Bridge Removal, A-16-062, I-295 Ramp over Ten Mile 73% Complete
    # 77888 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/24/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    JRC: Phase II installing loam at INF-2, excavation and subgrade for I-95 box widening. Scheduled work hours are Monday through Friday, 7:00 AM to 3:30 PM.
    Additional Info
    I-95 SB restricted from 3 lanes to 2 lanes as per Phase III TMP within the construction zone. All operations occurring behind barrier.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/19/2018
    Project Initiation Form PIF Entered 04/19/2018
    Project Initiation Form PRC Submitted 04/19/2018
    Project Review Committee PRC Approved 06/05/2018
    Project Status Advertised 08/26/2023
    Project Management
    100% Design 100% Package Received 05/05/2023
    25% Design 25% Package Received 08/17/2022
    75% Design 75% Package Received 01/25/2023
    75% Design 75% Package Comments to DE 02/27/2023
    Final Design PS&E Received 06/27/2023
    Final Design PS&E Received - Resub 1 07/20/2023
    Final Design PS&E Received - Resub 2 07/26/2023