SPENCER- BRIDGE REPLACEMENT, S-23-012, NORTH SPENCER ROAD (ROUTE 31) OVER THE SEVEN MILE RIVER
The proposed bridge project consists of replacing the existing bridge structure with a new single span bridge overpass structure. There will be no pedestrian accommodation improvements, however the useable shoulder will be increased making it safer for bicyclists to cross the bridge.
Location:
  • Town of Spencer
  • Construction Begins: Spring 2024
    Resident Engineer: Peter Kurt
    Construction Bid Price: $2,887,802.00
    District: District 3

    Contracts (2) Progress
    # 101631 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide and bridge projects, for the purpose of maintaining Final
    # 125779 -- Construction Contract
    Bridge Replacement, S-23-012, North Spencer Road (Route 31) over the Seven Mile River 5% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 06/11/2024
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/26/2018
    Project Initiation Form PIF Entered 04/26/2018
    Project Initiation Form PRC Submitted 04/26/2018
    Project Review Committee PRC Approved 07/19/2018
    Project Status Advertised 04/13/2024
    Project Management
    100% Design 100% Package Received 06/06/2023
    100% Design 100% Package Comments to DE 07/13/2023
    25% Design 25% Package Received 02/18/2022
    25% Design 25% Package Comments to DE 05/25/2022
    25% Design 25% Package Approved 01/18/2023
    25% Design Design Public Hearing 09/15/2022
    75% Design 75% Package Received 01/17/2023
    75% Design 75% Package Comments to DE 03/24/2023
    Final Design PS&E Received 09/14/2023
    Final Design PS&E Received - Resub 1 10/16/2023
    Final Design PS&E Received - Resub 2 11/06/2023
    Final Design PS&E Received - Resub 3 01/09/2024
    Consultant Contract Process Scope to DE 07/10/2020
    Consultant Contract Process NTP Issued 09/11/2021