Project Description:
WORCESTER- BRIDGE RECONSTRUCTION OF W-44-083, HARRISON STREET OVER I-290 & W-44-093, LAUREL STREET OVER I-290
The project will consist of superstructure replacement and substructure repairs of the Harrison and Laurel Street bridges over I-290 in the City of Worcester.
Location:
  • City of Worcester
  • Construction Begins: Spring 2025
    Resident Engineer: Webster Larkin Sr
    Construction Bid Price: $19,898,470.00
    District: District 3

    Contracts (2) Progress
    # 129075 -- Construction Contract
    Bridge Reconstruction of W-44-083, Harrison Street over I-290 & W-44-093, Laurel Street over I-290 21% Complete
    # 77863 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 04/09/2025
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/08/2018
    Project Initiation Form PIF Entered 05/08/2018
    Project Initiation Form PRC Submitted 05/08/2018
    Project Review Committee PRC Approved 07/19/2018
    Project Status Advertised 12/28/2024
    Project Management
    100% Design 100% Package Received 04/26/2024
    25% Design 25% Package Received 08/25/2022
    25% Design 25% Package Comments to DE 11/23/2022
    25% Design 25% Package Approved 10/07/2022
    25% Design Design Public Hearing 05/02/2023
    75% Design 75% Package Received 10/06/2023
    Final Design PS&E Received 08/26/2024
    Final Design PS&E to Peer Reviewer 10/22/2024
    Final Design Peer Review Comments to DE 11/12/2024
    Final Design PS&E Received - Resub 1 10/22/2024
    Final Design PS&E Received - Resub 2 11/22/2024