Project Description:
WORCESTER- BRIDGE RECONSTRUCTION OF W-44-083, HARRISON STREET OVER I-290 & W-44-093, LAUREL STREET OVER I-290
The project will consist of superstructure replacement and substructure repairs of the Harrison and Laurel Street bridges over I-290 in the City of Worcester.
Location:
  • City of Worcester
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2025
    Project Manager: Jacob Tanoglu
    Estimated Total Contract Cost: $20,107,231.70
    Estimated Total Federal Participating Construction Cost: $22,015,130.05
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: PS&E Received - Resub 1 (as of 10/22/2024 )

    Contracts (1) Progress
    # 77863 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: WORCESTER
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $20,199,674, Design Status = 75%
  • Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $16,159,739.20
    State Cost: $4,039,934.80
    Total Cost: $20,199,674.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/08/2018
    Project Initiation Form PIF Entered 05/08/2018
    Project Initiation Form PRC Submitted 05/08/2018
    Project Review Committee PRC Approved 07/19/2018
    Project Management
    100% Design 100% Package Received 04/26/2024
    25% Design 25% Package Received 08/25/2022
    25% Design 25% Package Comments to DE 11/23/2022
    25% Design 25% Package Approved 10/07/2022
    25% Design Design Public Hearing 05/02/2023
    75% Design 75% Package Received 10/06/2023
    Final Design PS&E Received 08/26/2024
    Final Design PS&E Received - Resub 1 10/22/2024