WORCESTER- BRIDGE RECONSTRUCTION OF W-44-083, HARRISON STREET OVER I-290 & W-44-093, LAUREL STREET OVER I-290
The project will consist of superstructure replacement and substructure repairs of the Harrison and Laurel Street bridges over I-290 in the City of Worcester.
Location:
  • City of Worcester
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2025
    Project Manager: Jacob Tanoglu
    Estimated Total Contract Cost: $20,095,731.70
    Estimated Total Federal Participating Construction Cost: $22,015,130.05
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: This project has been advertised for construction bids. (as of 12/28/2024 )

    Contracts (1) Progress
    # 77863 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: WORCESTER
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $20,199,674, Design Status = 75%
  • Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $16,159,739.20
    State Cost: $4,039,934.80
    Total Cost: $20,199,674.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/08/2018
    Project Initiation Form PIF Entered 05/08/2018
    Project Initiation Form PRC Submitted 05/08/2018
    Project Review Committee PRC Approved 07/19/2018
    Project Status Advertised 12/28/2024
    Project Management
    100% Design 100% Package Received 04/26/2024
    25% Design 25% Package Received 08/25/2022
    25% Design 25% Package Comments to DE 11/23/2022
    25% Design 25% Package Approved 10/07/2022
    25% Design Design Public Hearing 05/02/2023
    75% Design 75% Package Received 10/06/2023
    Final Design PS&E Received 08/26/2024
    Final Design PS&E to Peer Reviewer 10/22/2024
    Final Design Peer Review Comments to DE 11/12/2024
    Final Design PS&E Received - Resub 1 10/22/2024
    Final Design PS&E Received - Resub 2 11/22/2024