Project Description:
NORTON- INTERSECTION IMPROVEMENTS AT WEST MAIN STREET (ROUTE 123), NORTH WORCESTER STREET AND SOUTH WORCESTER STREET
Work on this project consists of traffic signal installation and roadway reconstruction to address safety concerns.
Location:
  • Town of Norton
  • Design Responsibility: Municipality
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2026
    Project Manager: Gregory Mischel
    Estimated Total Contract Cost: $2,386,005.99
    Estimated Total Federal Participating Construction Cost: $2,563,862.37
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: Design Public Hearing (as of 03/29/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: NORTON
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) Total Cost = $2,149,816 - CMAQ d) EC Score 51 of 100; h) Project Proponent - Norton; i) Status Pre 25%
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $1,719,853.60
    State Cost: $429,963.40
    Total Cost: $2,149,817.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/24/2018
    Project Need Form PNF Approved 01/11/2018
    Project Initiation Form PIF Entered 05/24/2018
    Project Initiation Form PIF Approved 05/24/2018
    Project Initiation Form PRC Submitted 05/25/2018
    Project Review Committee PRC Approved 07/19/2018
    Project Management
    25% Design 25% Package Received 12/10/2021
    25% Design 25% Package Comments to DE 03/23/2022
    25% Design Design Public Hearing 03/29/2023