Project Description:
BERKLEY- FREETOWN- LAKEVILLE- SOUTH COAST RAIL EARLY ACTION BRIDGE REPLACEMENTS
The Work for the South Coast Rail (SCR) Early Action Bridge project includes furnishing labor, materials, and equipment for the complete and satisfactory prosecution of the project in conformance with the Contract plans and specifications. The general scope of the work under the Base Contract includes the demolition and reconstruction of the bridges carrying the New Bedford Main Line over the Cotley River North in Berkley, MA, Cotley River South in Berkley, MA, Cedar Swamp River in Lakeville, MA, and Fall Brook in Freetown, MA as shown in the Contract Documents.
Location:
  • Town of Berkley
  • Town of Freetown
  • Town of Lakeville
  • Construction Begins: Spring 2019
    Resident Engineer: Rajat Gogoi
    Construction Bid Price: $21,977,824.00
    District: District 5

    Contracts (2) Progress
    # 106704 -- Construction Contract
    4 Railroad Bridge Replacements (Steel) along the South Coast Rail Line over the Cotley and Cedar Swamp Rivers and Fall Brook Completed
    # 65757 -- Design -- Geotechnical
    Work will consist of Geotechnical Review during the design of bridge structures and/or roadways owned by MassDOT and Cities and Towns throughout the Commonwealth. Final

    Bridges

    Contract Dates
    Notice to Proceed: 05/08/2019
    Contract Information
    Project Designer: Other
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/13/2018
    Project Need Form PNF Approved 06/13/2018
    Project Initiation Form PIF Entered 06/13/2018
    Project Initiation Form PIF Approved 06/13/2018
    Project Initiation Form PRC Submitted 06/21/2018
    Project Review Committee PRC Approved 07/19/2018
    Project Status Advertised 12/22/2018
    Project Management
    Final Design PS&E Received 12/17/2018
    Final Design PS&E to FAPRO 12/17/2018