Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NEW BEDFORD- INTERSECTION IMPROVEMENTS ON ACUSHNET AVENUE AT PECKHAM ROAD/SASSAQUIN AVENUE
Proposed improvements at the intersection are anticipated to include ADA compliant curb ramps, box widening along Peckham Road, mill/overlay along all four approaches, traffic signal installation, new pavement markings and signs.
Location:
  • City of New Bedford
  • Construction Begins: Autumn 2022
    Resident Engineer: Alfredo Nunez
    Construction Bid Price: $1,925,007.20
    District: District 5
    Current Status: • Traffic signal mast arm foundations began on 6/26/23. Utility relocation is needed to finish it. • Concrete sidewalk pouring started on 8/31/23. Utility relocation is needed to finish this work. • Utility poles installation (by Verizon) started on 10/10/23. Verizon started transferring cables on Peckham Road on 3/13/24. • Eversource started relocating their electric facilities on 10/25/23. Underground work began on 4/8/24. • Comcast started utility work on 1/3/24. Work was completed on 1/29/24. . Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. (as of 04/10/2024)

    Contracts (1) Progress
    # 119245 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) Acushnet Avenue at Peckham Road and Sassaquin Avenue 87% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/26/2022
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/13/2018
    Project Need Form PNF Approved 02/15/2018
    Project Initiation Form PIF Entered 06/13/2018
    Project Initiation Form PIF Approved 06/13/2018
    Project Initiation Form PRC Submitted 06/13/2018
    Project Review Committee PRC Approved 07/19/2018
    Project Status Advertised 07/23/2022
    Project Management
    100% Design 100% Package Received 03/04/2022
    25% Design 25% Package Received 01/14/2021
    25% Design 25% Package Comments to DE 03/18/2021
    25% Design Design Public Hearing 08/31/2021
    75% Design 75% Package Received 10/15/2021
    75% Design 75% Package Received 03/04/2022
    75% Design 75% Package Comments to DE 11/16/2021
    Final Design PS&E Received 03/04/2022
    Final Design PS&E Received - Resub 1 04/22/2022
    Final Design PS&E Received - Resub 2 04/29/2022