Project Description: |
NEW BEDFORD- INTERSECTION IMPROVEMENTS ON ACUSHNET AVENUE AT PECKHAM ROAD/SASSAQUIN AVENUE
Proposed improvements at the intersection are anticipated to include ADA compliant curb ramps, box widening along Peckham Road, mill/overlay along all four approaches, traffic signal installation, new pavement markings and signs.
|
Location: |
|
Construction Begins: | Autumn 2022 |
Resident Engineer: | Alfredo Nunez |
Construction Bid Price: | $1,925,007.20 |
District: | District 5 |
Current Status: | • Traffic signal mast arm installation started on 9/18/24. • Concrete sidewalk pouring started on 8/31/23. Utility relocation is needed to finish this work. • Utility poles installation (by Verizon) started on 10/10/23. Verizon started transferring cables on Peckham Road on 3/13/24. Verizon started splicing cables on 9/3/24. Verizon is working on removal of old cables and utility poles. • Comcast started utility work on 1/3/24. Work was completed on 1/29/24. • Eversource started relocating their electric facilities on 10/25/23. All electrical work was completed on 6/4/24. • Bi-weekly utility meetings with Verizon started being held on 8/9/24. . Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. (as of 11/13/2024) |
|
Bridges |
|
|
|