Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
GREENFIELD- RESURFACING AND RELATED WORK ON MONTAGUE CITY ROAD
This project seeks to resurface and provide pedestrian accommodations on Montague City Road in Greenfield, from the intersections of Route 5/10 (cheapside intersection project) to the intersection of Mountain Road near the entrance to the General Pierce bridge, for a total of 1 mile. In addition to resurfacing, the project will replace the existing sidewalks on the south/east side of Montague Road, and construct new pedestrian facilities where non-existent. ADA compliant ramps and crossings will also be installed.
Location:
  • Town of Greenfield
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2025
    Project Manager: Eric I Nova
    Estimated Total Contract Cost: $4,880,874.00
    Estimated Total Federal Participating Construction Cost: $5,458,776.30
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Franklin Regional Council of Governments.
    District: District 2
    Current Status: 100% Package Received (as of 10/05/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Franklin Regional Council of Governments
    Location: Municipality
    Cities: GREENFIELD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • MPO (TEC) Project Score 59/100.
  • Decreased CMAQ and added STBG via STIP Action 7.
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $380,000.00
    State Cost: $95,000.00
    Total Cost: $475,000.00
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $3,401,921.60
    State Cost: $850,480.40
    Total Cost: $4,252,402.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/14/2018
    Project Need Form PNF Approved 06/14/2018
    Project Initiation Form PIF Entered 06/14/2018
    Project Initiation Form PIF Approved 06/14/2018
    Project Initiation Form PRC Submitted 06/14/2018
    Project Review Committee PRC Approved 07/19/2018
    Project Management
    100% Design 100% Package Received 10/05/2023
    25% Design 25% Package Received 09/22/2021
    25% Design 25% Package Comments to DE 03/17/2023
    25% Design Design Public Hearing 11/16/2022
    75% Design 75% Package Received 12/15/2022
    75% Design 75% Package Comments to DE 03/17/2023