Project Description:
GREENFIELD- RESURFACING AND RELATED WORK ON MONTAGUE CITY ROAD
This project seeks to resurface and provide pedestrian accommodations on Montague City Road in Greenfield, from the intersections of Route 5/10 (cheapside intersection project) to the intersection of Mountain Road near the entrance to the General Pierce bridge, for a total of 1 mile. In addition to resurfacing, the project will replace the existing sidewalks on the south/east side of Montague Road, and construct new pedestrian facilities where non-existent. ADA compliant ramps and crossings will also be installed.
Location:
  • Town of Greenfield
  • Construction Begins: Autumn 2025
    Resident Engineer: Brendon Ewell
    Construction Bid Price: $3,531,444.00
    District: District 2

    Contracts (1) Progress
    # 131825 -- Construction Contract
    Resurfacing and Related Work on Montague City Road

    Bridges

    Contract Dates
    Notice to Proceed: 09/30/2025
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/14/2018
    Project Need Form PNF Approved 06/14/2018
    Project Initiation Form PIF Entered 06/14/2018
    Project Initiation Form PIF Approved 06/14/2018
    Project Initiation Form PRC Submitted 06/14/2018
    Project Review Committee PRC Approved 07/19/2018
    Project Status Advertised 08/02/2025
    Project Management
    100% Design 100% Package Received 10/05/2023
    100% Design 100% Package Comments to DE 11/13/2023
    25% Design 25% Package Received 09/22/2021
    25% Design 25% Package Comments to DE 03/17/2023
    25% Design Design Public Hearing 11/16/2022
    75% Design 75% Package Received 12/15/2022
    75% Design 75% Package Comments to DE 03/17/2023
    Final Design PS&E Received 10/29/2024
    Final Design PS&E Received - Resub 1 02/10/2025