Project Description:
PEABODY- INDEPENDENCE GREENWAY EXTENSION
Location:
  • City of Peabody
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2024
    Project Manager: Stephanie Upson
    Estimated Total Federal Participating Construction Cost: $3,007,750.00
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: 25% Package Comments to DE (as of 08/18/2021 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: PEABODY
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • TAP revised from $1,396,180.00 to $1,275,870 via STIP Action 6.
  • Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $1,020,696.00
    State Cost: $255,174.00
    Total Cost: $1,275,870.00

    Planned Federal FY: 2024
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: PEABODY
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction; CMAQ+TAP Total Cost = $3,368,680; MPO Evaluation Score = 34; TAP Proponent = Peabody
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $1,578,000.00
    State Cost: $394,500.00
    Total Cost: $1,972,500.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/19/2018
    Project Need Form PNF Approved 04/12/2018
    Project Initiation Form PIF Entered 06/19/2018
    Project Initiation Form PIF Approved 06/19/2018
    Project Initiation Form PRC Submitted 06/19/2018
    Project Review Committee PRC Approved 07/19/2018
    Project Management
    25% Design 25% Package Received 05/03/2021
    25% Design 25% Package Comments to DE 08/18/2021