Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DENNIS- CULVERT REPLACEMENTS ON ROUTE 6A OVER SESUIT CREEK
Proposed project would replace two existing 24" reinforced concrete pipes with new culverts that would be adequately sized hydraulically to be resilient to severe storms, reduce maintenance requirements (sediment removal), pass diadromous fish, and reduce impacts of flooding on the roadway. The culverts will likely be reconstructed with headwalls and wingwalls to mitigate the ongoing side-slope failure experienced at the site. A third culvert to the east will be evaluated, and may be repaired or replaced as needed. The roadway would be reconstructed within the project limits.
Location:
  • Town of Dennis
  • Construction Begins: Autumn 2022
    Resident Engineer: Alfredo Nunez
    Construction Bid Price: $4,296,970.90
    District: District 5

    Contracts (2) Progress
    # 120182 -- Construction Contract
    Culvert Replacements and Related Work along a Section of Route 6A (Main Street) over Sesuit Creek 15% Complete
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/02/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/19/2018
    Project Need Form PNF Approved 06/14/2018
    Project Initiation Form PIF Entered 06/19/2018
    Project Initiation Form PIF Approved 06/19/2018
    Project Initiation Form PRC Submitted 06/20/2018
    Project Review Committee PRC Approved 07/19/2018
    Project Status Advertised 09/10/2022
    Project Management
    100% Design 100% Package Received 04/26/2022
    25% Design 25% Package Received 06/17/2020
    75% Design 75% Package Received 06/17/2020
    75% Design 75% Package Comments to DE 07/24/2020
    Final Design PS&E Received 08/05/2022
    Final Design PS&E Received - Resub 1 08/23/2022
    Final Design PS&E Received - Resub 2 09/12/2022
    Final Design PS&E Received - Resub 3 09/21/2022