Project Description:
PALMER- WILBRAHAM- GUARDRAIL UPGRADES AND RELATED WORK ON I-90 (MM 58.9- 63.3)
Location:
  • Town of Palmer
  • Town of Wilbraham
  • Construction Begins: Winter 2019/2020
    Resident Engineer: Mark Joy
    Construction Bid Price: $2,821,418.25
    District: District 2

    Contracts (1) Progress
    # 109549 -- Construction Contract
    Guardrail Repairs and Replacements and Related Work along a Section of Interstate 90 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/21/2020
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Western Turnpike
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/22/2018
    Project Initiation Form PIF Entered 06/22/2018
    Project Initiation Form PRC Submitted 06/22/2018
    Project Review Committee PRC Approved 07/19/2018
    Project Status Advertised 08/31/2019
    Project Management
    100% Design 100% Package Received 08/30/2018
    100% Design 100% Package Received 04/01/2019
    Final Design PS&E Received 04/01/2019
    Final Design PS&E to FAPRO 08/26/2019