Project Description:
ARLINGTON- SPY POND SEDIMENT REMOVAL
The work will include removing drainage sediments from the outlet of the Route 2 drainage system at Spy Pond
Location:
  • Town of Arlington
  • Construction Begins: Summer 2020
    Resident Engineer: Martin McGowan
    Construction Bid Price: $1,872,836.00
    District: District 4

    Contracts (3) Progress
    # 111309 -- Construction Contract
    Spy Pond Dredging and Stormwater Improvements along a Section of Route 2 (Concord Turnpike) Completed
    # 77884 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/17/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/11/2018
    Project Need Form PNF Approved 07/11/2018
    Project Initiation Form PIF Entered 07/11/2018
    Project Initiation Form PIF Approved 07/11/2018
    Project Initiation Form PRC Submitted 07/12/2018
    Project Review Committee PRC Approved 07/19/2018
    Project Status Advertised 05/09/2020
    Project Management
    100% Design 100% Package Received 11/05/2019
    25% Design 25% Package Received 06/17/2019
    25% Design 25% Package Comments to DE 07/18/2019
    75% Design 75% Package Received 11/05/2019
    75% Design 75% Package Received 11/05/2019
    Final Design PS&E Received 04/17/2020
    Final Design PS&E to FAPRO 05/07/2020