Project Description:
WORCESTER- KELLEY SQUARE SAFETY IMPROVEMENTS ON MADISON STREET AND VERNON STREET
The purpose of the project is to improve safety and traffic operations at the Kelley Square intersections (the junction of Madison Street, Vernon Street, Millbury Street, Water Street, Harding Street, and Green Street), and roadway improvements on the section of Madison Street from Kelley Square to the railroad overpass just west of Gold Street. The project scope includes likely intersection improvements at the Vernon Street intersections with the I-290 WB and EB Ramps. Physical modifications to the bridge carrying Vernon Street over I-290 are not anticipated, however striping modifications should be considered to accommodate future year traffic volumes.
Location:
  • City of Worcester
  • Construction Begins: Autumn 2019
    Resident Engineer: Stephen Shamoian
    Construction Bid Price: $14,683,748.25
    District: District 3

    Contracts (3) Progress
    # 108887 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at Kelley Square along Madison, Vernon and Adjacent Streets Completed
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 86790 -- Design -- Services
    AutoCAD Base Plan Surveying Services Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/27/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/27/2018
    Project Need Form PNF Approved 06/29/2018
    Project Initiation Form PIF Entered 07/27/2018
    Project Initiation Form PIF Approved 07/27/2018
    Project Initiation Form PRC Submitted 07/30/2018
    Project Review Committee PRC Approved 07/30/2018
    Project Status Advertised 07/20/2019
    Project Management
    100% Design 100% Package Received 04/29/2019
    25% Design 25% Package Received 02/11/2019
    25% Design 25% Package Comments to DE 02/19/2019
    25% Design Design Public Hearing 02/27/2019
    75% Design 75% Package Received 04/29/2019
    Final Design PS&E Received 06/12/2019
    Final Design PS&E to Peer Reviewer 06/12/2019
    Final Design PS&E to FAPRO 07/08/2019
    Final Design PS&E Received - Resub 1 06/27/2019